Maintenance Procedure

Lead

Document

Notes

Scrambler Alignment Procedure

M. Sirk & S. Jelinsky

View file
nameFinal Scrambler Alignment Procedure.pptx

Fiber block installation Procedure

Winlight

View file
name23119-003-PRO002-A Fiber block integration procedure.pdf

Released

Agitator Reel Removal and Fiber
Setup Procedure

S. Gibson
M. Sirk

Draft document in-work

Spectrograph Installation Procedure

K. Rider

Status
colourYellow
title

funding-limited

TBC

Outline document generated, procedure refined with 3x operations at UCB.

Spectrograph Removal Procedure

K. Rider

Status
colourYellow
title

funding-limited

TBC

Outline document generated, procedure refined with 3x operations at UCB.

Chamber Pump-down Procedure

K. Rider

Status
colourYellow
title

funding-limited

TBC

Outline document generated, procedure refined with >5x operations at UCB.

Chamber Vent Procedure

K. Rider

Status
colourYellow
title

funding-limited

TBC

Outline document generated, procedure refined with >5x operations at UCB.

Shutter Replacement Procedure

S. Gibson

Hollow Cathode Lamp Replacement
Procedure

S. Gibson

Cal Unit Alignment Procedure

S. Gibson & S. Halverson

Status
colourYellow
titleTBC

Waiting for filter replacement. Will generate during filter installation.

Etalon Maintenance Procedure

C. Schwab

Status
colourYellow
titleTBC

Not yet started

Detector Cool-down Procedure

K. Rider

Status
colourYellow
title

funding-limited

TBC

Outline document generated, procedure refined with >5x operations at UCB.

Detector Warm-up Procedure

K. Rider

Status
colourYellow
title

funding-limited

TBC

Outline document generated, procedure refined with >5x operations at UCB.

LFC Maintenance Procedure

Menlo Systems

Status
colourYellow
titleTBC

A maintenance training session with Menlo is part of our contract but has not happened yet.

...

Other Procedures

Various notes sent to summit staff from the KPF team regarding adjustments or changes.

Most of these were one-time procedures, and will not need to be repeated. However,

they are collected here for reference.

Description

Procedure

Notes

Archon XVBias Board Removal

View file
nameKPF_Archon_Repair_Guide.pdf

Performed on the Green Archon after XVBoard started failing.

The XVBias board is only needed for the thicker (100um) STA devices; since both KPF CCDs are 30um-thick it can be removed.

Note the Red Archon also has this board installed but it has not been removed as of June 2023.

Archon Grounding Strap Installation

View file
nameKPF_Grounding-061523.pptx

The Archons were showing some fixed-pattern noise. This occurred at SSL and was fixed with better grounding of the Archons. These instructions show how to better ground the Archons to the vacuum chamber.

Ca HK Trigger Measurements

View file
nameHK Voltmeter tests.pptx

HK Galil Voltage Divider - Resistor Cahnge

View file
nameHK Galil Voltage Divider Modifications.pdf

Etalon Computer Re-Install

View file
nameEtalon computer re-install.pdf

Connections for the etalon computer to be re-installed after it was at headquarters for the WMKO OS install.

LFC Computer Network Change

View file
nameLFC Computer Network Change.pdf

The LFC was originally on the ops network; these instructions explained how to move it to the KPF Private Network (it’s current setup)

“Motor Off” Jumper Install for Optical Bench Isolator Motor Galil

View file
nameBench Isolator Motors Galil - MO Jumper Installation.pdf

This jumper prevents the motors from turning on inadvertently when the Galil is powered on.

Exposure Meter Shelf - Assembly Details

View file
nameExposure Meter Shelf Assembly Details.pptx