Maintenance Procedure | Lead | Document | Notes | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Scrambler Alignment Procedure | M. Sirk & S. Jelinsky |
| |||||||||
Reformatter Fiber Block Installation Procedure | Winlight |
| Released | ||||||||
Agitator General Maintenance Procedure | M. Sirk |
| |||||||||
Agitator Reel Removal Procedure | S. Gibson |
| Original draft. | ||||||||
Spectrograph Installation Procedure | K. Rider |
| Outline document generated, procedure refined with 3x operations at UCB. | ||||||||
Spectrograph Removal Procedure | K. Rider |
| Outline document generated, procedure refined with 3x operations at UCB. | ||||||||
Chamber Pump-down Procedure | K. Rider |
| Outline document generated, procedure refined with >5x operations at UCB. | ||||||||
Chamber Vent Procedure | K. Rider |
| Outline document generated, procedure refined with >5x operations at UCB. | ||||||||
Scrambler Source-Select Shutter Replacement Procedure | S. Gibson |
| |||||||||
Scrambler Sci/Sky (Timed) Shutter Replacement Procedure | S. Gibson |
| |||||||||
Hollow Cathode Lamp Replacement | S. Gibson |
| |||||||||
Cal Unit Alignment Procedure | S. Gibson & S. Halverson |
| Waiting for upgraded filters. Will generate procedure during filter installation. | ||||||||
Etalon Maintenance Procedure | C. Schwab |
| Not yet started | ||||||||
Detector Cool-down Procedure | K. Rider |
| Outline document generated, procedure refined with >5x operations at UCB. | ||||||||
Detector Warm-up Procedure | K. Rider |
| Outline document generated, procedure refined with >5x operations at UCB. | ||||||||
LFC Maintenance Procedure | Menlo Systems |
| A maintenance training session with Menlo is part of our contract but has not happened yet. |
...