Maintenance Procedure

Lead

Document

Notes

Scrambler Alignment Procedure

M. Sirk & S. Jelinsky

View file
nameFinal Scrambler Alignment Procedure.pptx

Reformatter Fiber Block Installation Procedure

Winlight

View file
name23119-003-PRO002-A Fiber block integration procedure.pdf

Released

Agitator General Maintenance Procedure

M. Sirk

View file
nameKPF_Agitator_Maintenance_Procedure_V1.0.pptx

Agitator Reel Removal Procedure

S. Gibson

View file
nameKPF_I&T_Proc_Template_060520-1_Agitator Fiber Install - very first draft.docx

Original draft.

Spectrograph Installation Procedure

K. Rider

Status
colourYellow
titleTBC

Outline document generated, procedure refined with 3x operations at UCB.

Spectrograph Removal Procedure

K. Rider

Status
colourYellow
titleTBC

Outline document generated, procedure refined with 3x operations at UCB.

Chamber Pump-down Procedure

K. Rider

Status
colourYellow
titleTBC

Outline document generated, procedure refined with >5x operations at UCB.

Chamber Vent Procedure

K. Rider

Status
colourYellow
titleTBC

Outline document generated, procedure refined with >5x operations at UCB.

Scrambler Source-Select Shutter Replacement Procedure

S. Gibson

View file
nameInvalid file id - bb413823-f2fd-4357-b84c-85e385b317e2

View file
nameKPF - Scrambler Source-Select Shutter Replacement Procedure v1.0.docx

Scrambler Sci/Sky (Timed) Shutter Replacement Procedure

S. Gibson

View file
nameKPF - Scrambler Sci-Sky Timed Shutter Replacement Procedure v1.0.pdf

View file
nameKPF - Scrambler Sci-Sky Timed Shutter Replacement Procedure v1.0.docx

Hollow Cathode Lamp Replacement
Procedure

S. Gibson

View file
nameKPF - Hollow Cathode Lamp Change Procedure v1.1.pdf

View file
nameKPF - Hollow Cathode Lamp Change Procedure v1.1.docx

Cal Unit Alignment Procedure

S. Gibson & S. Halverson

Status
colourYellow
titleTBC

Waiting for upgraded filters. Will generate procedure during filter installation.

Etalon Maintenance Procedure

C. Schwab

Status
colourYellow
titleTBC

Not yet started

Detector Cool-down Procedure

K. Rider

Status
colourYellow
titleTBC

Outline document generated, procedure refined with >5x operations at UCB.

Detector Warm-up Procedure

K. Rider

Status
colourYellow
titleTBC

Outline document generated, procedure refined with >5x operations at UCB.

LFC Maintenance Procedure

Menlo Systems

Status
colourYellow
titleTBC

A maintenance training session with Menlo is part of our contract but has not happened yet.

...