Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

\uD83E\uDD45 Goals

\uD83D\uDDE3 Discussion topics

Time

Item

Presenter

Notes

1:02

Words from John

John

words

  • Call for proposals

    • end of 25A will be end of operations for NIRES

    • will begin a 1 year hibernation

    • at end of 26A same for ESI

  • NIRC2 and OSIRIS also potential retirements, but contingent on Liger and SCALES

  • 25A call will also have K1 shutdown, detailed dates TBD

  • Lots going on in 25A

1:1513

Words from Jim

Jim

  • wordsNew semester = new SA support schedule

    • Aug and sept is up

    • Working on Nov

  • SA recruitment

    • down selected from 6 to 4 to bring out

    • Confirmed that we will hire two positions

  • Night Log Tickets

    • Lots from recent AO run

1:19

Summit power outages, UNO, AFP, and instruments

Jim

  • continue discussion from last time?

2:26

  • Come up with procedure

  • Then “scriptify” it

  • Then decide if you want it automatically

  • RM: are there types of shutdowns we should consider?

    • CJ: No levels, just plan on extended power outage with no staff.

    • Some computer is computer room will be listed to remain on

  • Homework: Send to Jim document with procedure

1:30

NIRC2 FITS Header Issues

Carlos

  • Recent issues where some FITS headers did not get handled properly

    • RTI ingestion overwrote some header values because of changes

  • Some AO keywords in NIRC2 headers were using bad CAKE files referencing old WFS. Change should have happened at RTC upgrade.

    • The CAKE is a lie.

  • Jim: for AO we “need more cops on the beat” because dev team doesn’t know some of these issues and the instrument-AO-telescope system is complex.

1:38

Pau!

Next meeting lead: ?????Greg

✅ Action items

  •  

⤴ Decisions

...