Replacement Difficulty Key:
...
Subsystem | Item Description | Manufacturer & Part Number | QTY in System | Cost / Lead Time* | Replacement Difficulty | Replacement Notes | General Notes | Spares in Hand? | Impact of Failure | |||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
FIU | ADC Prism Rotators | Micronix PR-50-C0017 | 2x | $5,500 ea / 10-12 weeks |
| Requires:
| None |
| ||||||||||||||||||||||||||
FIU | H&K Fiber Stage | Micronix PPX-32CR-C0002 | 1x | $4,500 ea / 10-12 weeks |
| Requires:
| None |
| ||||||||||||||||||||||||||
FIU | Calibration Fold Mirror Stage | Micronix PPS-20-C0035 | 1x | $4,400 ea / 10-12 weeks |
| Requires:
| None |
If it failed out-of-beam:
If it failed in-beam:
| ||||||||||||||||||||||||||
FIU | Guide Detector | First Light | Imaging CRED-
| 1x | Have asked Jim Thorne for details$39k / |
| Requires removing the FIU from the AO Bench to gain access to detector. | None |
| |||||||||||||||||||||||||
Ca HK | Ca HK Detector | Andor Newton 920 (with UV-optimized CCD) | 1x | $37k / 12 weeks |
| Requires opening Ca HK Spectrometer (after swinging it to a horizontal state). | None |
| ||||||||||||||||||||||||||
Cal Unit | Octagon Stepper Motor | Thorlabs NR360S | 1x | $2,700 |
| The rotation stage is accessible on the outside of the Calibration Bench, and mechanically this is a straightforward change. The difficulty lies in re-aligning the fold mirror mounted on the rotation stage, so that is directs the light from all sources onto the various fibers. | None |
| ||||||||||||||||||||||||||
Cal Unit | ThAr Lamp | Green Scientific G858A | 2x (1x Daily, | $405 |
| The lamps are easily accessible on the exterior of the Calibration Unit. | Consumable item. | 1 spareNo current spares 6 are on order * updated * | If one lamp fails:
If both lamps of the same type fail:
| |||||||||||||||||||||||||
Cal Unit | UNe Lamp | Photron P863 | 2x (1x Daily, | $825 |
| The lamps are easily accessible on the exterior of the Calibration Unit. | Consumable item. | 4 spares | ||||||||||||||||||||||||||
Cal Unit | HCL Power Supply | Photron P209 Hollow Cathode Lamp Power Supply and Green Scientific G200 | 4x (1x Th-Ar Daily, 1x U-Ne Daily, 1x Un-Ne Gold) | Green Scientific Supply: $730 |
| The HCL power supplies are easily accessible within the Calibration Rack. | 1x Green Scientific Power Supply | If one supply fails:
If two supplies of the same type fail:
If three supplies fail:
| ||||||||||||||||||||||||||
Cal Unit | Broadband Source | Thorlabs SLS201L | 2x (1x Octagon, 1x Flat Field) | $1,200 |
| The broadband sources are easily accessible under the Calibration Bench. | Consumable item. | None |
| |||||||||||||||||||||||||
Cal Unit | Intensity Monitor Stage | Newmark MSL-50-21 | 1x | $1,100 |
| Mechanically the stage is easy to remove, and the intensity monitor detector is simply mounted (on a post with no careful alignment requirements). Marked as medium difficulty given the care required to avoid damaging the bare optical fibers within the Calibration Unit enclosure. | None |
| ||||||||||||||||||||||||||
Cal Unit | Filter Wheel | Thorlabs FW102C | 3x (1x Octagon, 1x Flat Field) | $1,300 |
| Mechanically the filter wheels are easy to remove with no careful alignment requirements. Marked as medium difficulty given the care required to avoid damaging the bare optical fibers within the Calibration Unit enclosure. | None |
| ||||||||||||||||||||||||||
Cal Unit | Compensator Motor | Newport TRA12PPD | 4x | Need TBD | ||||||||||||||||||||||||||||||
Cal Unit | Shutters | Uniblitz DSS25B | 6x (2x Cal Bench, | $540 ea / |
| The various shutters are designed to be easily removable from their mounts. Marked as medium difficulty given time required to open the enclosure to access shutter, and care required while working around exposed optics and fibers. | Consumable item. | 3 spares | If the Calibration shutters fail:
If the SoCal, HK Spectrometer, or Flat Field Fiber shutters fail:
| |||||||||||||||||||||||||
Cal Unit | Etalon Super Continuum | NKT SuperK EVO | 1x | $33.5k for new device, $8.5k to refurbish existing device. Lead time: 4-6 weeks. |
| The SuperK is easily accessible within Etalon Rack. | Consumable item. | None |
| |||||||||||||||||||||||||
Exposure Meter | Exposure Meter Detector | SBIG Aluma 47-10 | 1x | $15k / |
| Requires opening the Exposure Meter enclosure. Detector is on mounting that is designed to be removable. | None |
| ||||||||||||||||||||||||||
LFC | PCF Fiber | Have asked Brett Smith for details | Consumable item.Menlo Systems | 1 |
| impactFiber System | Scrambler Timed Shutter | Uniblitz NS65B | 1x | $1,280 /
| Brett Smith (WMKO) installed the replacement when the PCF fiber failed. He said it took about an hour, but one needs to be slow and methodical. Covers, module, output fibers are removed one of which, the IR, is in a tight space. PCF module location is set by pins. | Consumable item. | None | 1 spare
| This shutter is designed to be easily removable from the scrambler. Marked as medium difficulty given time required to open the enclosure to access the shutter, and care required while working around exposed optics and fibers. | Consumable item. |
| |||||||||||||||||
Fiber System | Scrambler Timed Shutter | Uniblitz NS65B | 1x | $1,280 / |
| major impact | This shutter controls the
|
This shutter is designed to be easily removable from the scrambler. Marked as medium difficulty given time required to open the enclosure to access the shutter, and care required while working around exposed optics and fibers.
Consumable item.
1 spare
Status | ||||
---|---|---|---|---|
|
This shutter controls the exposure time of the main spectrometer. Would not be able to take spectra until shutter is replaced.
Fiber System
Scrambler Source Select Shutter
Uniblitz RS20B
2x
$550 each (minimum quantity was 10 last time we ordered). Lead time: 5-6 weeks
Status | ||||
---|---|---|---|---|
|
These shutters are designed to be easily removable from the scrambler. Marked as medium difficulty given time required to open the enclosure to access the shutters, and care required while working around exposed optics and fibers.
Consumable item.
10 spares
Status | ||||
---|---|---|---|---|
|
If one of these shutters fails in a closed state, that light path (Science or Sky) cannot be used until the shutter is replaced.
Fiber System
Agitator Motor
Galil BLM-N23-50-1000-B
1x
$500 /
1-2 weeks
(in 2018)
Status | ||||
---|---|---|---|---|
|
Motor is accessible on the outside of the agitator. A flex coupling is used between the motor and the agitator mechanism, so no careful alignment required. Marked as medium difficulty given the agitator is located within the crypt (not easily accessible and potential permits required).
None
Status | ||||
---|---|---|---|---|
|
Observations could continue however the radial velocity precision will be impacted.
Vac Cart
Turbo Pump
Leybold TurboVac 450iX
1x
$7,700
Status | ||||
---|---|---|---|---|
|
Vacuum chamber gate valve must be closed, and Vac Cart enclosure opened to replace pump. Vacuum pressure within chamber will be rising during this time (affecting instrumental stability), making this replacement time-sensitive. A WMKO turbo cart could be connected to the chamber during the replacement to help minimize the vacuum pressure change.
None
Status | ||||
---|---|---|---|---|
|
Chamber would start to lose vacuum pressure
During time required to obtain replacement pump, vacuum pressure would rise significantly and reset the instrumental stability time series.
Vac Cart
Roots Pump
Leybold EcoDry 65 Plus
1x
$9,600
Status | ||||
---|---|---|---|---|
|
Vacuum chamber gate valve must be closed, and Vac Cart enclosure opened to replace pump. Vacuum pressure within chamber will be rising during this time (affecting instrumental stability), making this replacement time-sensitive. A WMKO turbo cart could be connected to the chamber during the replacement to help minimize the vacuum pressure change.
None
Status | ||||
---|---|---|---|---|
|
Chamber would start to lose vacuum pressure
During time required to obtain replacement pump, vacuum pressure would rise significantly and reset the instrumental stability time series.
Vac Cart
Isolator Stepper Motors
Lin Engineering 4118M-06S-22RO
5x
Status | ||||
---|---|---|---|---|
|
Requires warming up CCDs, venting main spectrometer vacuum chamber, and opening chamber door(s) to gain access to the motors under the optical bench. Depending on the motor’s location, the Vac Cart, Aux Rack and LN2 Autofill system might need to be disconnected and moved out of the way so the chamber door can open.
Used very infrequently (mainly for initial alignment of bench or realigning after a significant earthquake). Powered off when not in use.
None
Status | ||||
---|---|---|---|---|
|
Loss of one motor could likely be compensated for through adjustment of the other four.
It is very unlikely we would vent the chamber only to replace one of these motors.
Aux Rack
Cryostat Ion Pumps
Gamma 3SDI1V5KNN (3S TiTan)
4x
$770 /
6-7 weeks
Gamma 3SDI1V5KNN (3S TiTan)
4x
$770 /
6-7 weeks
Status | ||||
---|---|---|---|---|
|
Requires warming up CCDs, venting main spectrometer vacuum chamber, and removing the large camera-access flange on the side of the vacuum chamber. The ion pumps can be “re-conditioned” at WMKO and re-used.
500 hours at 1e-4mbar
5,000 hours at 1e-5mbar
50,000 hours at 1e-6mbar
500,000 hours at 1e-7mbar
None
Each cryostat has two ion pumps.
If one fails:
Status colour Green title minor impact If both fail:
Status colour Red title major impact CCD thermal control will be lost
Aux Rack
LN2 Pumps
Instec LN2-SYS
2x
Status | ||||
---|---|---|---|---|
|
The pumps are easily accessible on the LN2 cart in the basement. Marked as medium difficulty given the steps involved:
power down the appropriate Instec controller;
connect the new pump and power it on;
turn the Instec controller back on;
ensure Instec set point is correct and temperature control enabled.
There is also some risk involved, as care must be taken to avoid water vapor getting into the lines (leading to ice blocking the lines). If ice blocks the lines then the CCD must be warmed up and the lines purged (with a major disruption to the instrument stability timeline).
1 brand-new spare;
1 used spare
Each cryostat has two ion pumps.
If one fails:
Status | ||||
---|---|---|---|---|
|
Status | |||
---|---|---|---|
|
Requires warming up CCDs, venting main spectrometer vacuum chamber, and removing the large camera-access flange on the side of the vacuum chamber. The ion pumps can be “re-conditioned” at WMKO and re-used.
500 hours at 1e-4mbar
5,000 hours at 1e-5mbar
50,000 hours at 1e-6mbar
500,000 hours at 1e-7mbar
None
|
CCD thermal control cannot be maintained with the LN2 pump running. The CCD will start to warm up.
Aux Rack
Instec Controller
Instec mK2000B
2
$5000 / 4-6 weeks
Status | ||||
---|---|---|---|---|
|
The pumps are easily accessible on the LN2 cart in the basement. Marked as medium difficulty given the software steps involved:
power down the appropriate Instec controller and disconnect cables;
connect the new controller and power it on;
ensure Instec set point is correct and temperature control enabled.
1 spare has been ordered
Status | ||||
---|---|---|---|---|
|
CCD thermal control
Aux Rack
LN2 Pumps
Instec LN2-SYS
cannot be maintained without the Instec system running. The CCD will start to warm up.
LN2 Cart
*updated*
Autofill System
2x solenoids
Status | ||||
---|---|---|---|---|
|
The
solenoids and other components are
accessible on the LN2
power down the appropriate Instec controller;
connect the new pump and power it on;
turn the Instec controller back on;
ensure Instec set point is correct and temperature control enabled.
cart in the basement. Marked as medium difficulty given there is some risk involved, as care must be taken to avoid water vapor getting into the lines (leading to ice blocking the lines). If ice blocks the lines then the CCD must be warmed up and the lines purged (with a major disruption to the instrument stability timeline).
1 used spare
3x Solenoids
Also shared spares available for:
Maple PLC (and HMI and I/O modules
temperature sensors
pressure transducers
Status | ||||
---|---|---|---|---|
|
CCD thermal control cannot be maintained with the LN2 pump runningwithout LN2 in the KPF dewars. The CCD will start to warm up.
Aux Rack
Instec Controller
Instec mK2000B
2
Computer
*updated*
kpfserver
ASL Lancelot
2884-SRT
1
$10k /
1 week (in 2021)
Status | |
---|---|
|
|
The pumps are easily accessible on the LN2 cart in the basement. Marked as medium difficulty given the software steps involved:
power down the appropriate Instec controller and disconnect cables;
connect the new controller and power it on;
ensure Instec set point is correct and temperature control enabled.
|
Backup computer already installed within KPF Calibration Rack. When switching to the backup computer, the USB cable for the Exposure Meter detector needs to be moved from kpfserver to the backup computer.
However the WMKO-standard OS and files need to be installed.
1 spare
Status | ||||
---|---|---|---|---|
|
CCD thermal control cannot be maintained without the Instec system running. The CCD will start to warm up.
LN2 Cart
Autofill Solenoids
2x
If kpfserver goes down, we lose remote control of the instrument (and all telemetry)