Time | Item | Presenter | Notes |
---|
1:03 | Words from John | John | |
1:05 | Words from Randy | Randy | |
1:23 | SSC: Strategic Plan | Randy | Randy: We will have role, but different than last time John: trying not to create busywork. SAs should have real input, not just be notetakers.
|
1:26 | TeamKeck | Luca | |
1:31 | LRIS-R Commissioning Plan | Sherry, Marc, Percy | Arrives on April 6 Full schedule on spreadsheet LRIS off sky on April 16 (warm red side dewar) Install dewar in April 19 Engineering April 27-28, May 6 (all first half nights) Luca: what about operational scripts (e.g. focus)? WillD and Kyle have been working on adapting focus low level software to run on new machine. This is low level s/w not scripts. Kyle will move software to new machine on 17th, but that is basic functionality of focus mechanism, not scripting. Sherry: been trying scripts on linux VM Luca: need to come up with list of needed scripts for going on sky. Sherry: we have document
Randy: where do we put things so everyone can see it? Confluence. Kyle: Solaris machine will still exist and will have keyword access to new detector Are there access issues with the recent fall protection areas that were defined around cass? Carolyn: do any SAs want/need fall training? Is scheduling for OAs, will send email. Luca: how conservative/aggressive is schedule? Marc: the previous (Mark-III) upgrade was done in just a couple days Kyle: that change was purely detector hardware, so this is difference scope with software and computer architecture, first ARCONS controller. Randy/Marc: could be noisier than lab (not uncommon), but don’t anticipate dramatic problems in first run
Kyle: first science is 7-15 (last eng is 6th) Marc: shared slide presented at SSC meeting Any changes to slit mask design? No immediate changes. No gap on red side which was the limiting factor (blue gap is smaller: 12” vs 30”). No plan for project to deal with DRPs, but PypeIt will get modified Readout is now 42 seconds vs. 200 seconds Will not have windowing (deferred by project) MIRA and SAT will still be on blue side due to mechanism move times Connie is interested in studying what went wrong with current mosaic. Not funded, but is of interest.
|
2:11 | Outreach Ambassadors | Josh | |
2:15 | Telescope Support Schedule | Randy | |
2:23 | Pau! | | |