Provided here is the list of maintenance procedure that KPF itemized at the Pre Ship Review.

Maintenance Procedure

Lead

Document

Notes

Scrambler Alignment Procedure

M. Sirk & S. Jelinsky

Fiber block installation Procedure

Winlight

Released

Agitator Reel Removal and Fiber
Setup Procedure

S. Gibson
M. Sirk

Draft document in-work

Spectrograph Installation Procedure

K. Rider

TBC

Outline document generated, procedure refined with 3x operations at UCB.

Spectrograph Removal Procedure

K. Rider

TBC

Outline document generated, procedure refined with 3x operations at UCB.

Chamber Pump-down Procedure

K. Rider

TBC

Outline document generated, procedure refined with >5x operations at UCB.

Chamber Vent Procedure

K. Rider

TBC

Outline document generated, procedure refined with >5x operations at UCB.

Shutter Replacement Procedure

S. Gibson

Hollow Cathode Lamp Replacement
Procedure

S. Gibson

Cal Unit Alignment Procedure

S. Gibson & S. Halverson

TBC

Waiting for filter replacement. Will generate during filter installation.

Etalon Maintenance Procedure

C. Schwab

TBC

Not yet started

Detector Cool-down Procedure

K. Rider

TBC

Outline document generated, procedure refined with >5x operations at UCB.

Detector Warm-up Procedure

K. Rider

TBC

Outline document generated, procedure refined with >5x operations at UCB.

LFC Maintenance Procedure

Menlo Systems

TBC

A maintenance training session with Menlo is part of our contract but has not happened yet.


Other Procedures

Various notes sent to summit staff from the KPF team regarding adjustments or changes.

Most of these were one-time procedures, and will not need to be repeated. However,

they are collected here for reference.

Description

Procedure

Notes

Archon XVBias Board Removal

Performed on the Green Archon after XVBoard started failing.

The XVBias board is only needed for the thicker (100um) STA devices; since both KPF CCDs are 30um-thick it can be removed.

Note the Red Archon also has this board installed but it has not been removed as of June 2023.

Archon Grounding Strap Installation

The Archons were showing some fixed-pattern noise. This occurred at SSL and was fixed with better grounding of the Archons. These instructions show how to better ground the Archons to the vacuum chamber.

Ca HK Trigger Measurements

HK Galil Voltage Divider - Resistor Cahnge

Etalon Computer Re-Install

Connections for the etalon computer to be re-installed after it was at headquarters for the WMKO OS install.

LFC Computer Network Change

The LFC was originally on the ops network; these instructions explained how to move it to the KPF Private Network (it’s current setup)

“Motor Off” Jumper Install for Optical Bench Isolator Motor Galil

This jumper prevents the motors from turning on inadvertently when the Galil is powered on.

Exposure Meter Shelf - Assembly Details










  • No labels