Leak Test - September 23, 2021

Leak Test - September 23, 2021


Table of Contents:


Test Description

Leak test after chamber had been pumping down for 5.5 days, after first installation of bench support cart and MLI inside chamber.

Chamber interior during test.

Test Data

Note data in these files go back to midnight, or 10 hrs before test was started.

Description

File

Description

File

kpfvac service telemetry

(vac gauges, vac pump telemetry)

kpfmet service telemetry

(Vaisala temp, pressure, RH)


Test Log

Time

Who

Description

Time

Who

Description

10:07 am

SG

Gate valve closed

10:09 am

SG

Turbo pump stopped

12:50 pm

SG

Chamber pressure over last hour looks fairly linear (by eye), with a rate of +0.0027 Torr per hour.

1:40 pm

SG

Gate valve power outlet on PDU turned back on. Gate valve remained closed as expected.

3:02 pm

SG

Will updated the dispatcher for VCH_LOVAC and VCH_HIVAC

3:30 pm

SG

Pressures on either side of gate basically equal. Turned turbo pump on to force lower pressure on pump side of gate valve.

3:32 pm

SG, CS

Opened gate valve

 

Related content

2024-01-09: at 1:40pm HST: KPF Red deltaT = 75 mK
2024-01-09: at 1:40pm HST: KPF Red deltaT = 75 mK
More like this
Vacuum Pump System
Vacuum Pump System
More like this
2023-04-18 at 08:27 HST: Green Detector Full Warm Up
2023-04-18 at 08:27 HST: Green Detector Full Warm Up