1:02 | Words from Jim | Jim | Mentor for HPA senior? Leo starts Nov 11, think about training plan Offer to Belen is out or imminent John and Marc at UCO-AC meeting TK proposals due soon (about 1.5 weeks from now)
|
1:12 | K1 Az wrap | Jim/Carolyn | K1 over-travel damaged Az cable wrap 9/20 No one hurt Quick action by Eric/TonyR prevented serious damage Put back in place 9/21 Incident investigation ongoing As with incidents like this, there were multiple things that went wrong
|
1:15 | Cal Association | MaxB | For new instruments, what are the Updating an existing ICD for new instruments Minimum cals Calibration association ideas Loaded Q: what about existing instruments? Josh: require an enumeration of instrument modes, each with an order of mag estimates of how long cals will take Josh: don’t impose a particular calibration association strategy, but ask for one Max: also require doing DCS scrubbing to protect target info during cals Max: how to manage a list of bad files for the DRP
|
1:44 | New Slitmask Database Webpage | Michael | |
1:54 | Summit power shutdown | Jim/All | Summit automatic transfer switch (ATS) and breaker replacement scheduled for Nov 6/7 (install/test) Full power off on summit for up to 2 hours What are the instrument risks? Will write up for decision makers
Percy may not be able to make this, but gave some thoughts: Risk of troubles while booting a system will delay the power on of Lakeshores or other temperature controllers While normally robust to comms issues, perhaps a Lakeshore comes up incorrectly Would greatly prefer to have a UPS Is there a specific order to bring servers up for each instrument? Does booting a server also bring up the software automatically?
Current ATS (switches between HELCO and generator) has been deemed end of life and needs to be replaced All power will be off, generator and HELCO Estimated to take 1-2 hours CCRs will be off. Guideline is for instruments to be able to handle 1 hour of CCR off for reconfig Instrument UPSs will still be active, but will not last for the full 1-2 hours unless we shut off some of the draw. Next SA meeting: have draft for each instrument Meet next week?
|
2:21 | Astropy Workshop | Sherry | |
2:23 | KSM download | All | So, anything interesting happen? Need to make a NIRES piñata with SA morale money Max: have suggested people apply to KVSP for DRP work e.g. PypeIt DEIMOS for new detector, no current plan PypeIt just got NSF POSE grant, includes 0.5 FTE for Keck for 2 years
|
2:38 | Pau! | | Next lead: Rosalie |