Battery need
Prefer to keep both spectrograph and imager Lakeshore powered up with UPSs
Procedure Before power down
On Nov 4: Sherry run
osirisStartWarmup
to
set both detector target temperatures to 80K
lock all the mechanisms
start temperature and pressure logging
keep detectors powered on byoids.powerdown=0
andosds.powerdown=0
On Nov 6, by 8:30 am: Sherry power off spec and imag detectors by
oids.powerdown=1
andosds.powerdown=1
, then runosirisDisconnect
On Nov 6, IT turn off:
osiris-drp
vm-osiris
osirisimag
osirisspec
osiris-control2
osiris-control1
osirisserverOn Nov 6, summit turn off CCR right before 9:30
Procedure during the power down
None
Procedure to bring back the system
Summit turn on CCR
IT Bring up:
osirisserver
osirisspec
osirisimag
vm-osiris
osiris-drpIf the computers are up:
Sherry will run
osirisConnect
which will power on the lakeshores and instrument
osiris-control1
osiris-control2
will be connected after osirisConnect is complete.Sherry will run
osirisStartCooldown
to set spec and imag detector target temperature to 72K and 70KSherry checks if the heaters for spec and imag detectors are up and running and keep both detectors at target temperature . It will likely take more work to bring up the spec detector heater, see Kd1-32369