| | | |
|---|
1:00 | Words from Jim | Jim | Thank you for past year, lots of challenges Working on possible restoration of slew speed on K1 Jim away tomorrow through Jan 6. Greg will be delegate for observing decisions. Jim has draft of schedule for 26A, will circulate. Up on share point now. Rosalie: SCALES is officially delayed. Pre-ship review in March, will miss AO shutdown. HAKA still says they will hit window (still has a review to pass).
|
1:11 | Words from John | John | Thanks for another year of science enabled. Been a challenging year. 5 year planning process has kicked off as of today Was in DC last week. Things trending positively on federal funding. Rich out next week. John will be here. AAS coming up. John out Jan 2-9. RC: Are we looking for new partners? JO: Have been many discussions with board. Long range uncertainty about costs after lease renewal, potentially higher load of shared services costs. Partners: UC, CIT, NASA (contributed capital) Scientific Partners: Swinburne (nights/year threshold, voting seat on SSC) UH is special case. Act 255 put 7% floor on UH time, currently have 10% on K1, 15% on K2. Affected by lease negotiation
RM: Community outreach reporting form?
|
1:31 | Update on Instrument PMs | Grant | Met with summit instrument folks eMaint is still the tool for PMs Ask Tod to submit entries, make changes, etc. GH will start putting PMs on summit schedule in place of generic “Instrument PMs” task GH working with summit crew to re-evaluate existing PMs and update them if needed Not currently thinking about PMs that SAs would do, only the hands on PMs for techs/engineers Action Item: Send hands on tasks to Grant to see if they exist in eMaint. Keith will be helping Tod run eMaint
|
1:53 | KPIC Retirement | Jim | |
1:55 | KNIT Meetings | Leo | |
2:02 | DEIMOS Detector Upgrade | Michael | |
2:07 | Pau! | | Next Lead: @Jim Lyke Next meeting Jan 15 |