  • On Nov 4: Sherry run osirisStartWarmup to
    set both detector target temperatures to 80K
    lock all the mechanisms
    start temperature and pressure logging
    keep detectors powered on by
    oids.powerdown=0 and osds.powerdown=0

  • On Nov 6, by 9 am: Sherry power off spec and imag detectors by oids.powerdown=1 and osds.powerdown=1, then run osirisDisconnect

  • On Nov 6, IT turn off:
    osiris-drp
    vm-osiris
    osirisimag
    osirisspec
    osirisserver
    osiris-control2
    osiris-control1
    osirisserver

Procedure during the power down

...

Procedure to bring back the system

  • IT Bring up:
    osirisserver
    osiris-control1
    osiris-control2
    osirisserver
    osirisspec
    osirisimag
    vm-osiris
    osiris-drp

  • If the computers are up:

    • Sherry will run osirisConnect which will power on the lakeshores and instrument

    • Sherry will run osirisStartCooldown to set spec and imag detector target temperature to 72K and 70K

    • Summit turns on CCR

    • Sherry checks if the heaters for spec and imag detectors are up and running and keep both detectors at target temperature . It will likely take more work to bring up the spec detector heater, see Kd1-32369