Subsystem

Status at Pre-Ship Review

Current Status

Outstanding Issues That Affect Operations

Outstanding Issues For KPF Team

Ca H&K Spectrometer

  • Throughput requirement met by calculation

    • measurement deferred to on-sky

  • Met all other requirements

  • Trouble with trigger signal to start exposures has meant it has not been in regular use

  • On-sky throughput measurement still TBD

    • requires testing of HK ADC within FIU

  • Continued troubleshooting of trigger signal

  • On-sky throughput tests

Calibration Unit

  • Could not fully test the Calibration Unit at SSL since compensator motors had very long lead and were not in-hand.

  • Calibration Unit was set into a state that allowed use but was not the final configuration.

  • New plan is to not use motors but purchase filters with higher tolerances. 

  • This will make for a simpler system going forward (and one easier to maintain as 4 less motors involved, no look-up table to maintain)

  • There have been issues with Photron lamps and power supplies

    • solved by moving to Green Scientific lamps and supplies

    • However there are still 3x Photron power supplies in the system

  • Filter purchase waiting on funding; will install filters during servicing mission.

LFC

  • LFC availability was sparse.  A combination of sub-optimal thermal variations in the high-bay (10’s of degrees F thermal variation over 12 hours) and incomplete software automation precluded extended operation of the LFC at SSL.

  • Comb has been operational but there has been significant down-time due to Menlo hardware and software issues.

  • Occasional help with installing hardware (i.e. PCF fiber modules)

  • Maintaining comb via software control

Etalon

  • Was not available for tests at SSL.

  • Current etalon has been used regularly

  • However etalon light source (SuperK) is failing our moving out of alignment

  • Troubleshoot SuperK-to-etalon alignment (underway)

  • Secure another SuperK to have a spare on hand

Cryostats/CCDs

  • Fully passed majority of requirements

    • Some requirements were just missed but deemed OK.

  • Fringing was significantly worse than requirement, plan was to correct in software

  • Some fixed-noise patterns on CCDs caused by insufficient grounding

  • Charge Transfer Efficiency (CTE) issue on one quadrant of Green CCD

  • Fringing patttern still present

  • Grounding straps to be attached between Archon and vacuum chamber (underway)

  • Change readout mode on Green CCD to avoid CTE issue

  • Investigate ways to minimize fringing impact within DRP

Environmental Control System

  • Vacuum Chamber met requirements

  • Thermal enclosure not designed/built

  • Thermal enclosure to be installed later this year

Servicing mission items:

  • bring linear potentiometers online (provide bench position feedback)

  • bring gate valve position feedback online

Exposure Meter

  • Throughput requirement met by calculation

    • measurement deferred to on-sky

  • Met all other requirements

  • In regular use

  • Test using the Exposure Meter in an automated way to terminate an exposure at the correct signal-to-noise ratio.

  • Determine on-sky throughput (and compare to main spectrometer)

Fiber Injection Unit

  • Optical performance and alignment requirements met

  • Centering stars on fibers has proven to be challenging

  • FVCs have been more challenging to use than expected.

  • Prisms within Science arm ADC appear to not be set correctly

  • Will update this section once Josh returns from vacation

Optical Fibers

  • All requirements met

  • Backup Simulateous Cal fiber was damaged during installation. There are no current plans to build a replacement.

Agitator

  • Was not tested at SSL

  • In regular use

  • Quantify agitator performance via “agitator on” vs. “agitator off” test.

Instrument Control Software

  • Nearly all dispatchers written (only exposure meter, LFC, and etalon TBC)

  • Minimal alarms in place

  • All dispatchers now operational

  • “testall” script in regular use

  • Alarm system fully functional with important alarms in place

  • Archon has occasional trigger-signal issues

  • Backup computer is on summit but not operational (needs OS installed)

  • Potential need for help troubleshooting Archon trigger signal issue

  • Installation of backup computer

  • Add more alarms for various telemetry items

Observing GUI

  • Sketches and plans but no code before PSR

  • In regular use

  • Two areas still need some effort:

    • tip/tilt control and status GUI

    • automated exposure meter control of exposures

Spectrometer

  • Throughput requirement met by calculation

    • measurement deferred to on-sky

  • Met all other requirements

  • Fiber block in reformatter is slightly out of alignment

  • Green channel focus is soft in one corner of CCD

  • Flat field fiber system needs slight realignment

  • Ion pumps on cryostats are generating low levels of stray light

  • Throughput matches model except at bluest end of full bandpass

    • could be a symptom of incorrect ADC correction

  • Servicing mission items:

    • fiber block re-alignment

    • Green channel focus adjustment

    • flat field fiber re-alignment

    • add baffles to ion pumps

SoCal

  • Not included within PSR scope

LN2 Autofill System

  • Original LN2 cart and LN2 transfer plumbing was complete

  • Initial tests showed major heat losses within transfer plumbing, which caused GN2 back-pressure issues and prevented dewar fills

  • System was completely re-designed to correct these issues

  • Autofill system now in regular use, and KPF dewars are filled from supply dewars located in K2 machinery room