Subsystem | Status at Pre-Ship Review | Current Status | Outstanding Issues That Affect Operations | Outstanding Issues For KPF Team |
---|
Ca H&K Spectrometer | | | | |
Calibration Unit | Could not fully test the Calibration Unit at SSL since compensator motors had very long lead and were not in-hand. Calibration Unit was set into a state that allowed use but was not the final configuration.
| New plan is to not use motors but purchase filters with higher tolerances. This will make for a simpler system going forward (and one easier to maintain as 4 less motors involved, no look-up table to maintain)
| | |
LFC | | | | |
Etalon | | | | |
Cryostats/CCDs | Fully passed majority of requirements Fringing was significantly worse than requirement, plan was to correct in software
| Some fixed-noise patterns on CCDs caused by insufficient grounding Charge Transfer Efficiency (CTE) issue on one quadrant of Green CCD Fringing patttern still present
| | |
Environmental Control System | | | | Servicing mission items: |
Exposure Meter | | | | |
Fiber Injection Unit | •Optical performance and alignment requirements met | | On-sky acquisition and guiding requirements met? – check list sent to Josh for CAPS FVCs have been more challenging to use than expected. ADC prism counter-rotation offsets likely not correct
| |
Optical Fibers | •All requirements met | | | |
Agitator | •Was not tested at SSL | | | |
Instrument Control Software | •Nearly all dispatchers written (only exposure meter, LFC, and etalon TBC) •Minimal alarms in place | | | Update: All dispatchers now operational “testall” script operational and in use Alarm system fully functional with important alarms in place
To-do: |
Observing GUI | | | | |
Spectrometer | | | | |
SoCal | | | | |