Battery need
Prefer to keep both spectrograph and imager Lakeshore powered up with UPSs
Procedure Before power down
Sherry will power off and warm both detectors to 80K after the Nov 3 science run.
Procedure during the power down
None
Procedure to bring back the system
Bring up
napili
(osirisserver) first, thenpuunoa
(spec target computer),kuiaha
(imag target computer),olowalu
(osirisdrp)If the computers are up:
Sherry will run
osirisConnect
which will power on instrument, start servers, and checks out detectors.Sherry will check mechanism health, and then power on and cool down both detectors.