•Trouble

Subsystem

PSR Requirements Summary

Outstanding Issues That Affect Operations

Other Outstanding Issues

Ca H&K Spectrometer

•Met requirements

•(Throughput was calculated not measured)

  • Throughput requirement met by calculation

    • measurement deferred to on-sky

  • Met all other requirements

  • Trouble with trigger signal to start exposures

•Has
  • (troubleshooting underway)

  • Does spectrum need to be moved?

  • Has on-sky throughput been checked?

•Does spectrum need to be moved?

Calibration Unit

•Could
  • Could not fully test the Calibration Unit at SSL since compensator motors had very long lead and were not in-hand.

•Calibration
  • Calibration Unit was set into a state that allowed use but was not the final configuration.

•Plan at PSR was to install compensating motors to account for filter wedge angle differences causing mis-alignments

•New
  • New plan is to not use motors but purchase filters with higher tolerances

and avoid using motors
  • .  Filter purchase waiting on funding; will install filters during servicing mission.  This will make for a simpler system going forward (and one easier to maintain as 4 less motors involved, no look-up table to maintain)

•Lamp
  • Lamp issues, power supply issues

(now
    • Now perhaps solved with Green Scientific lamps and supplies?

)

LFC

  • LFC availability was sparse.  A combination of sub-optimal thermal variations in the high-bay (10’s of degrees F thermal variation over 12 hours) and incomplete software automation precluded extended operation of the LFC at SSL.

  • Comb has been operational but there has been significant down-time due to Menlo hardware and software issues.

Etalon

•Was
  • Was not available for tests at SSL.

•SuperK
  • SuperK failing

•Is
  • Is this our final etalon?  Plans for a replacement?

Cryostats/CCDs

•Passed
  • Fully passed majority of requirements

.
•Some
    • Some requirements were just missed but deemed OK.

•Fringing
  • Fringing was significantly worse than requirement, plan was to correct in software

  • Noise issues (procedure in-hand for better grounding)

  • Has fringing correction been looked at yet?  (science impact not operational)

  • CTE issue on one Green quadrant

Noise issues (procedure in-hand for better grounding)

Environmental Control System

•Vacuum •Thermal
  • Vacuum Chamber met requirements

•Have
  • Thermal enclosure not designed/built

  • Thermal enclosure to be installed later this year.

  • Linear potentiometers not in regular use (will be re-initialized during servicing mission)

  • Gate valve position monitoring not yet implemented (will occur during servicing mission)

Exposure Meter

•Met requirements

•(Throughput was calculated not measured)

  • Throughput requirement met by calculation

    • measurement deferred to on-sky

  • Met all other requirements

  • Have we checked this?  “The flux at the EM detector shall be at minimum 1% of the flux at the main spectrometer CCD”

•Above
  • Above also needed for automatic exposure termination

•Has
  • Has that been done tried yet??

Fiber Injection Unit

•Optical performance and alignment requirements met

•On
  • On-sky acquisition and guiding requirements met? – check list sent to Josh for CAPS

•FVCs
  • FVCs have been more challenging to use than expected.

•ADC
  • ADC prism counter-rotation offsets likely not correct

Optical Fibers

•All requirements met

  • Backup Simulateous Cal fiber was damaged during installation. There are no current plans to build a replacement.

Agitator

•Was not tested at SSL

•Has
  • No issues; has been in routine operation on the summit

•Have

  • Have we done an agitator on / agitator off performance verification test??

Instrument Control Software

•Nearly all dispatchers written (only exposure meter, LFC, and etalon TBC)

•Minimal alarms in place

Update:

•All
  • All dispatchers now operational

•“testall”
  • “testall” script operational

(
  • and in use

?)
•Alarm systems
  • Alarm system fully functional

•Plan
  • with important alarms in place

To-do:

  • Plan to add more alarms

•Archon
  • Archon trigger issues

•Backup computer still TBD

  • Backup computer in-hand but not operational (needs OS installed)

Observing GUI

•Sketches
  • Sketches and plans but no code

•Fully operational??

Spectrometer

•Met

  • Throughput requirement met by calculation

    • measurement deferred to on-sky

  • Met all other requirements

•(
  • Throughput

was calculated not measured)•Throughput
  • matches model except at bluest end of full bandpass

•Current thought – this is
    • could be a symptom of

the
    • incorrect ADC correction

being off

SoCal