Subsystem | PSR Requirements Summary | Outstanding Issues |
---|---|---|
Ca H&K Spectrometer | •Met requirements •(Throughput was calculated not measured) | •Trouble with trigger signal to start exposures •Has on-sky throughput been checked? •Does spectrum need to be moved? |
Calibration Unit | •Could not fully test the Calibration Unit at SSL since compensator motors had very long lead and were not in-hand. •Calibration Unit was set into a state that allowed use but was not the final configuration. | •Plan at PSR was to install compensating motors to account for filter wedge angle differences causing mis-alignments •New plan is to purchase filters with higher tolerances and avoid using motors. Filter purchase waiting on funding; will install filters during servicing mission. This will make for a simpler system going forward (and one easier to maintain as 4 less motors involved, no look-up table to maintain) •Lamp issues, power supply issues (now perhaps solved with Green Scientific lamps and supplies?) |
LFC | LFC availability was sparse. A combination of sub-optimal thermal variations in the high-bay (10’s of degrees F thermal variation over 12 hours) and incomplete software automation precluded extended operation of the LFC at SSL. | Comb has been operational but there has been significant down-time due to Menlo hardware and software issues. |
Etalon | •Was not available for tests at SSL. | •SuperK failing •Is this our final etalon? Plans for a replacement? |
Cryostats/CCDs | •Passed majority of requirements. •Some requirements were just missed but deemed OK. •Fringing was significantly worse than requirement, plan was to correct in software | Has fringing correction been looked at yet? (science impact not operational) CTE issue on one Green quadrant Noise issues (procedure in-hand for better grounding) |
Environmental Control System | •Vacuum Chamber met requirements • •Thermal enclosure not designed/built | Linear potentiometers not in regular use Gate valve position monitoring not yet implemented |
Exposure Meter | •Met requirements •(Throughput was calculated not measured) | •Have we checked this? “The flux at the EM detector shall be at minimum 1% of the flux at the main spectrometer CCD” •Above also needed for automatic exposure termination •Has that been done tried yet?? |
Fiber Injection Unit | •Optical performance and alignment requirements met | •On-sky acquisition and guiding requirements met? – check list sent to Josh for CAPS •FVCs have been challenging •ADC prism counter-rotation offsets likely not correct |
Optical Fibers | •All requirements met | • |
Agitator | •Was not tested at SSL | •Has been in routine operation on the summit •Have we done an agitator on / agitator off test?? |
Instrument Control Software | •Nearly all dispatchers written (only exposure meter, LFC, and etalon TBC) •Minimal alarms in place | •All dispatchers now operational •“testall” script operational (and in use?) •Alarm systems fully functional •Plan to add more alarms •Archon trigger issues •Backup computer still TBD • |
Observing GUI | •Sketches and plans but no code | •Fully operational?? |
Spectrometer | •Met requirements •(Throughput was calculated not measured) | •Throughput matches model except at bluest end of full bandpass •Current thought – this is a symptom of the ADC correction being off |