K1. Engineering
2020-05-21. Night 1 Engineering Proposal (this is ambitious)
UTStart | Duration (hh:mm) | Test | complet |
05:04 | 00:15 | Sunset/Dome open |
|
05:19 | 02:00 | PCS: fine screen, phasing |
|
07:20 | 00:10 | Switch to OSIRIS |
|
07:30 | 00:30 | Basic AO/OSIRIS checkout Stability IQ on bright star |
|
08:00 | 01:00 | OSIRIS HAM Check HD 90700 (single) HD 90823 (double) |
|
09:00 | 01:00 | OSIRIS post-service Server functionality post OS upgrade Orientation Offsets between OSPEC/OSIMG Offsets between OSPEC scales |
|
10:00 | 01:00 | OSIRIS Tellurics w/ & w/o TRICK dichroic Mostly SPEC Simultaneous IMAG if can |
|
11:00 | 01:00 | OSIRIS blank sky for wavelength solution |
|
12:00 | 01:00 | Repeat Tellurics or Imager throughputs as function of pupil |
|
13:00 | 00:10 | Switch to SSC |
|
13:10 | 00:50 | 45-star pointing test CW |
|
14:00 | 00:50 | 45-star pointing test CCW |
|
14:52 | - | 12-degree twilight |
|
15:33 | - | Sunrise |
|
2020-05-22. Night 2
StartUT | Duration | Test | complete |
05:04 | 00:16 | Sunset/Open Dome |
|
05:20 | 01:00 | MOSFIRE on-sky |
|
06:20 | 00:10 | Switch to OSIRIS |
|
06:30 | 00:45 | LGS checkout |
|
07:15 | 01:00 | KAPA laser optimization Wavelength Polarization Intensity Background w/ detuning |
|
08:15 | 02:00 | KAPA laser performance Spot size vs. El Pointing |
|
10:15 | 03:00 | KAPA LGS performance Imag IQ vs TT Rmag, EL SPEC IQ vs TT Rmag, EL Ref NGS measurement |
|
13:15 | 01:37 | TRICK functionality on GC |
|
14:52 | - | 12 degree twilight |
|
15:33 | - | Sunrise |
|
2020-05-23. Night 3
StartUT | Duration | Test | complete |
05:05 | 00:15 | Sunset/Open Dome |
|
05:20 | 01:00 | HIRESr on-sky |
|
06:20 | 00:10 | Switch to OSIRIS |
|
06:30 | 01:00 | LGS checkout |
|
07:30 | 01:30 | LBWFS Tests New LBImgAcq New LBMngr |
|
09:00 | 03:00 | KAPA LGS Performance IQ vs mag IQ vs off-axis distance IQ vs framerate IQ vs r0 Ref NGS measurement Dither performance |
|
12:00 | 02:51 | LIFT w/ TRICK |
|
14:51 | - | 12 degree twilight |
|
15:33 | - | Sunrise |
|