Shutdown is ~1.5 months
We have tended to specialize in K1 or K2, some of us will see K2 for the first time in a long time.
Pier repair is still looking for more people, so AJ and Danny might be pulled, so we could fill in on some instrument tasks.
PR team is acutely aware that K2 will still be on sky
Should instruments be covered in plastic to protect them?
There is a return to science concept that we will need to contribute to
Running the ACs warm as a dehumidifier
During test run, it took a week to settle out the pointing. Probably concrete cooling time.
Josh: need to think about cooling for multiple days before going on sky to equalize thermal masses
Jim: 2020 had a long shutdown which we can look at for experience
Exercise dome and shutters during pier repair?
Josh: pull secondary and store in mirror barn? Put First Contact over some optics? Pull or cover tertiary?
Dome might get warm, does this affect glycol cooling of instruments?
LRIS will be in Cass (nominally)
Should we pull it (especially if secondary is out)
Dome clean room will be partially disassembled