Time | Item | Presenter | Notes |
---|---|---|---|
1:07 | Words from John | John |
|
| Words from Randy |
|
|
1:22 | KPF update | Josh |
|
1:50 | Deimos mask design software update | Michael | Engineering successful for new mask design software. Some offsets between milled masks, likely related to mask blank seating. On sky alignment went well with targets well centered in slits. Plan to have first draft done in 2 weeks, full deployment for 23B. |
2:20 | Slitmask deadline scheduling | Carlos | DEIMOS and LRIS quite a few late masks submitted. We need to handle this in a way that we can get the masks milled on time. If we can change the deadline to 5 weeks before the deadline. |
2:25 | KCRM | Rosalie | Shipping Feb 8th, going up mountain Feb 26th |
2:30 | K1 Shutter | Carolyn | K1 Bottom Shutter install week of 13th |